Joint Southeast Campus Area Committee – March meeting
The Joint Southeast Campus Area Committee’s met yesterday. The main presentation was by a group of representatives from the St. Paul Catholic Center. The Center previously proposed building a new 14-story building on their current site on Library Mall. Those plans were rejected by the City of Madison because they violated the height restrictions for that portion of State Street. The Center is now proposing a scaled-down version of its original plan. This new plan doesn’t include student housing and will be 6-8 stories.
Representatives from St. Paul’s focused their presentation on the footprint and loading docks of the new facility. They wanted to demonstrate the need for a fire lane on State Street in front of the building. Representatives from the University seemed open to this request. Nothing was voted on or approved. The new plans will be presented to the City this summer. If approved then fundraising will begin. Officials expect to break ground in the next two years.
After the presentation from St. Paul’s, representatives from the University updated the committee on its current projects.
East Campus Mall – the portion under the Chazen addition will be completed by October. The rest will be completed in a couple years with the new Gordon Commons project.
Music Performance Building – this project is in the design phase. Half of the needed funds have been raised.
Memorial Union – this is also in the design phase. The first phase will focus on the Theater wing and it will start next year.
Hockey Center – breaking ground in April, the facility should be done in fall 2012.
Charter Street Plant – the natural gas facility is under construction. The biomass portion is on hold for now but it can be added in the future. The plant will stop burning coal in fall 2012.
Library Mall – phase 2 of the utility project has started.
Lake Street – construction between University and Lake Mendota will start after graduation and be completed by mid August.
Langdon Street – Lake St to Park St will be resurfaced in 2012.
State Street – Lake St to Park St will be resurfaced in 2013.
Union South – opening on April 15.
The next committee meeting is rescheduled for Monday, May 23.